EKO OBERHAUSEN (HOSPITAL)

Construction project: EKO OBERHAUSEN (HOSPITAL).
Size: approx. 4000 m²
Installation: January – August 2009
Task: New laying of a PVC floor covering on a new ZE with residual moisture and old subfloor
Installer: Heimdekor Huvers Borken
Development: subfloor assessment and recommendation for building by the technical application department by Forbo Eurocol Germany GmnH.
Design; Preparation: cracks and joints must be sealed with 816 Europlan Repair Duo epoxy putting compound and wave connectors.
Primer: 2 application layers of 042 Euroblock Turbo with a roller and a intermediate layer application with 070 Europrimer Fill.
Levelling compound: height compensation with 940 Europlan Quick and levelling with 977 Europlan Pro.
Laying and adhesion: Bonding of the PVC floor covering with 640 Eurostar Unicol as well as the gluing of the profiles with 650 Eurostar Fastcool.